GHA and RSLs would each build 3,000 houses as part of this agreement.
Originally, apart from a portion of new build just after transfer the RSL programme was intended to take effect after 7 years with GHA’s programme being completed before then.
Since then among other things the GHA's Demolition Programme has expanded considerably and during 2006 the Council with its partners approached Scottish Ministers to have the RSL programme rescheduled. Scottish Ministers approved the re-scheduling together with an Implementation Plan in October 2006.