Timescale: |
2001-10 |
|
Budget: |
£1.2 billion |
|
Partners: |
Glasgow Harbour Limited, Scottish Enterprise Glasgow and Strathclyde European Partnership |
|
Lead: |
Glasgow Harbour Limited (Peel Holdings Plc) and Glasgow City Council |
|
Target: |
To complete the regeneration of 49 hectares and over 3km of waterfront and to assist 270 unemployed people into work or further education. |
|
Status: |
Completed:
Demolition of former granaries, 2001-03; Phase 1 Clyde Walkway 2004; and Refurbishment of Meadowside underpass including community art project and completion of Phase 1, public park, 2005.
Consents:
Planning consent granted for 649 units, Phase 1, 2002;
Planning consent granted for 770 units, Phase 2, March 2005 and 651m² of commercial use;
Planning consent was granted for revised infrastructure, April 2005. Revised masterplan is submitted for trial office and residential was, including public space and proposed regional casino by MGM Mirage.
On site:
Construction of, Phase 1, 2002-06.
Phase 2 residential 2005-2008.
Infrastructure work associated with lowering Clydeside Expressway and improving access from district and local network. |
|
|
|
|
|
|
|
Activity: |
It is a mix-used development, which will see the building of more than 2500 new homes along with new business, retail and leisure areas.
Approximately 42% of the site will be developed as new parks with river walkways and cycle paths. There will be major investment to create new internal roads, lower the Clydeside Expressway at Partick, upgrade pedestrian connections from Partick to Glasgow Harbour and provide new transport links to the City Centre. |
|
|
|
|
|
|