Skip to content
Glasgow City Council

Tollcross - Tollcross Road

Project:

Spaces for People

Location:

Tollcross Road - from a point 50 metres west of the extended west kerbline of Crail Street, to Maukinfauld Road

Tollcross Road - between Wellshot Road and Anworth Street

Expected Work Start Date:

 20 July 2020

  

Measure(s):

  • Tollcross Road: south side of carriageway within the lay-by (west of Ogilvie Street) there will be approximately 10 metres of extended footway.
  • Tollcross Road: south side of carriageway within the lay-by (east of Ogilvie Street) there will be approximately 27 metres of extended footway.
  • Tollcross Road: south side of carriageway within the lay-by (opposite the junction of Murrayfauld Drive), there will be approximately 20 metres of extended footway.
  • Tollcross Road: north side of carriageway within the lay-by (east of Wellshot Road) there will be approximately 20 metres of extended footway.
  • Approximately 12 metres of no waiting at any time restrictions in the form of double yellow lines will be installed east of the footway widening works.

 

  • Tollcross Road: north side of carriageway within the lay-by (immediately east of Altyre Street) there will be approximately 17 metres of extended footway.
  • Approximately 20 metres of no waiting at any time restrictions in the form of double yellow lines will be installed within the lay-by adjacent to Nos. 997-1007 Tollcross Road.
  • Tollcross Road: south side of carriageway within the lay-by (between Altyre Street and Dalness Street) there will be approximately 46 metres of extended footway
  • Approximately 19 metres of no waiting at any time restrictions in the form of double yellow lines will be installed east of the footway widening works.

 

  • Tollcross Road: north side of carriageway within the lay-by (east of Dalness Street) there will be approximately 28 metres of extended footway.
  • Approximately 15 metres of no waiting at any time restrictions in the form of double yellow lines will be installed east of the footway widening works.

 

  • Tollcross Road: south side of carriageway within the lay-by (east of Dalness Street) there will be approximately 40 metres of extended footway.
  • Approximately 14 metres of no waiting at any time restrictions in the form of double yellow lines will be installed east of the footway widening works.
  • A further 16 metres of extended footway works will be installed immediately east of the proposed double yellow lines.

Tollcross (Tollcross Road)

Detail:

The temporary works will be in place from Monday 20 July 2020 for a minimum period of 10 weeks.

The temporary works will be reviewed in line with the Scottish Government's Covid-19 Framework for Decision Making 'Scotland's Route Map through and out of the crisis'.

Images of temporary measures following installation:

Tollcross 1

Tollcross 2

Tollcross 3

Tollcross 4

Tollcross 5

Share this page:

A to Z:

Council Services