Project:

Spaces for People

Location:

Parkhead: Westmuir St (between Gallowgate & Crail Street)

Expected Work Start Date:

22 July 2020

Expected Work Completion Date:

29 July 2020

Measure(s):

Westmuir Street: Both sides of carriageway will be narrowed by 2 metres between Gallowgate and Crail Street. Parking areas suspended whilst temporary restriction are in place.

Detail:

The temporary works will be in place  for a minimum period of 10 weeks.

The temporary works will be reviewed in line with the Scottish Government's Covid-19 Framework for Decision Making 'Scotland's Route Map through and out of the crisis'.

Parkhead (Tollcross Road and Westmuir Street)

Update: 14 December 2020

Spaces for People infrastructure is temporary and as such, agile. Measures can be mobilised relatively quickly as the need arises, and adjustments made to existing infrastructure after a period of review.

Following a monitoring period at this location, the temporary infrastructure has been removed.

Update: 16 September 2021

Following an independent review which recommended the retention of those Spaces for People measures that could realise long term sustainability and active travel benefits - temporary footway widening infrastructure across neighbourhoods will not be reinstated at this location/made permanent.